Board of Control Agenda

AGENDA

BOARD OF CONTROL

Tuesday, February 25, 2020

Mayor’s Conference Room: 8th Floor City Hall

9:00 AM


Ordinance 120/2018, Contract 2019-04

  1. Enter into Change Order No. 2 and final with Wenger Excavating, Inc. for the Ridgewood East Phase I Project Part 1 and Part 2 contract #2019-04 in the amount of ($400.87).  This represents the final additional quantities in the amount of $59,245.03 and deduct quantities in the amount of ($59,645.91) for a total final non-performance of ($400.87). This project is being managed by the Water Department


Ordinance 24/2019, Contract 2019-62

  • Enter into Change Order No. 2 and final with Wenger Excavating, Inc. for the Ridgewood East Phase II Project contract #2019-62 in the amount of $18,332.13.  This represents the additional quantities in the amount of $61,972.90 and deduct quantities in the amount of ($43,640.77) for a total addition of $18,332.13. This project is being managed by the Water Department


Ordinance 4/2020

  • Enter into a construction contract with Wenger Excavating, Inc. for the Aultman Cancer Center Utilities Relocation Project in the amount of $920,880.30. Department. This project is being managed by the Engineering Department.