Ordinance 244/2020
Enter into Change Order No. 3 with Northstar Asphalt, Inc. in the amount of $1,230.77 for the Paving Project, Phase 2, 3rd St. SE Resurfacing Project, GP 1339 due to final quantity adjustments and fuel escalation costs, resulting in a new contract amount of $564,838.47. This will also revise the substantial completion date to April 30, 2023, for the Engineering Department.