AGENDA
BOARD OF CONTROL


Tuesday, March 9, 2021
Mayor's Conference Room: 8th Floor City Hall
9:00 AM

1.

Ordinance 193/2019

Enter into Change Order No. 3 with WSP USA, Inc. in order to change the date of substantial completion for the Professional Planning and Design Services for the Neighborhood Development Master Plan and Redevelopment Strategy from February 1, 2021 to May 24, 2021 as a result of setbacks and delays due to COVID-19.  There will be no additional cost to the City.
2.

Codified Ordinance 107.07

Award and enter into contract with American Demolition, Inc. for the sale of scrap metal no longer needed for municipal purposes for $188.79 per ton for miscellaneous scrap for the Collection Systems Department and Service Center.
3.

Ordinance TBD

Enter into Change Order No. 1 with IBI Group U.S., Inc. in the amount of $83,956.00 for the design engineering services on the Colonial Blvd. Reconstruction Project, Phase 1, GP 1206, due to the extension of project limits and design for additional water main work, resulting in a new contract amount of $383,382.00.
4.

Ordinance 244/2020

Award and enter into contract with Noble Environmental Specialty Services, LLC for the Sugar Creek Water Treatment Plant Lagoon Cleanout, Removal and Disposal of Sludge in the amount of $81.30 per ton for Complete Sludge Removal; $3,242.50 per Lagoon for Mobilization and $56.00 per ton for landfill disposal cost.