AGENDA

SPECIAL BOARD OF CONTROL


Tuesday, July 6, 2021

Mayor's Conference Room: 8th Floor City Hall

8:30 AM


1.

Ordinance 58/2021

Award and enter into a construction contract with The Shelly Company in the amount of $2,643,655.60 for the 36th St. NW Storm Sewer & Road Reconstruction Project, Phase 2, GP 1270 for the Engineering Dept.

2.

Ordinance 78/2021

Enter into contract with Cargill, Inc. for the supply of road salt at a cost of $46.11 per ton for the 2021-2022 winter season pursuant to Ohio Revised Code Section 5513.01 (Ohio Department of Transportation Cooperative Purchasing Program).

3.

Ordinance 58/2021